4 82-4-301 1 82-4-302 3 82-4-303 82-4-304 82-4-305 82-4-306 82-4-307 82-4-308 82-4-309 82-4-310 82-4-311 82-4-312 1 82-4-313 82-4-314 82-4-315 82-4-321 82-4-322 82-4-323 82-4-331 82-4-332 82-4-334 2 82-4-335 3 82-4-336 1 82-4-337 82-4-338 82-4-339 82-4-340 82-4-341 82-4-342 82-4-349 82-4-350 3 82-4-351 82-4-352 82-4-353 82-4-354 1 82-4-355 82-4-356 82-4-357 1 82-4-360 1 82-4-361 82-4-362 82-4-367 82-4-371 82-4-372 1 82-4-375 1 82-4-376 1 82-4-377 82-4-378 1 82-4-379 82-4-380 82-4-381 82-4-390

Mont. Code Ann. § 82-4-380

(2015)

Periodic review required

(1) At least once every 5 years following department approval of a design document pursuant to 82-4-376 during mining, or as required in a reclamation plan approved pursuant to 82-4-336, the operator shall assemble a panel in accordance with the panel requirements in 82-4-377. A reasonable effort must be made to retain previous panel members.

(2) The panel shall:

(a) inspect the tailings storage facility;

(b) review the tailings operation, maintenance, and surveillance manual and records collected in association with the manual;

(c) interview people with responsibilities identified in the tailings operation, maintenance, and surveillance manual; and

(d) review annual engineer of record inspection reports, corrective action plans, records associated with construction, and any other aspect, plan, record, document, design, model, or report related to the tailings storage facility that the panel needs to review to ensure that the tailings storage facility is constructed, operated, and maintained as designed and is functioning, can be closed as intended, and meets acceptable engineering standards.

(3) The operator shall provide documents and records necessary for the panel to complete a periodic review.

(4) The panel shall prepare a report detailing the scope of review and include any recommendations resulting from the review.

(5) The panel shall immediately notify the department and the operator if there is an imminent threat to human health or the environment.

(6) The final review report must be signed by each panel member and provided to the department and the operator.

(7) The operator shall prepare a corrective action plan and schedule effectively implementing the recommendations included in the panel's report. The operator shall submit the corrective action plan and schedule to the panel within 60 days after receipt of the panel report.

(8) The panel shall review the corrective action plan and schedule to determine whether the corrective action plan and schedule proposed by the operator will effectively implement the recommendations included in the panel's report.

(9) Within 30 days after receipt of approval from the panel, the operator shall submit the corrective action plan with an implementation schedule to the department.

(10) Failure to implement the corrective action plan pursuant to the implementation schedule is subject to the provisions of 82-4-361 and 82-4-362.

Official Annotations archive.org, 2015 edition
History:
En. Sec. 9, Ch. 399, L. 2015 (SB 409 - Vincent, Chas (R) SD 1)