82-4-201 1 82-4-202 2 82-4-203 82-4-204 82-4-205 1 82-4-206 82-4-207 1 82-4-221 1 82-4-222 82-4-223 82-4-225 82-4-226 1 82-4-227 82-4-228 1 82-4-231 82-4-232 82-4-233 82-4-234 82-4-235 82-4-236 82-4-237 82-4-238 82-4-239 82-4-240 82-4-241 82-4-242 82-4-243 82-4-244 82-4-250 1 82-4-251 82-4-252 82-4-253 82-4-254

Mont. Code Ann. § 82-4-234

(2011)

Commencement of reclamation

The operator shall commence the reclamation of the area of land affected by the operator's operation as soon as possible after the beginning of strip mining or underground mining of that area in accordance with plans previously approved by the department. Those grading, backfilling, subsidence stabilization, topsoiling, and water management practices that are approved in the plans must be kept current with the operation as defined by rules of the board, and a permit or supplement to a permit may not be issued if, in the discretion of the department, these practices are not current.

Official Annotations archive.org, 2011 edition
History:
En. Sec. 13, Ch. 325, L. 1973
Amd. Sec. 25, Ch. 441, L. 1975
R.C.M. 1947, 50-1046
Amd. Sec. 3, Ch. 196, L. 1979
Amd. Sec. 8, Ch. 204, L. 2003 (HB 373 - Olson, Alan (R) HD 8)