Reclamation plan and specific reclamation requirements
(1) The reclamation plan must provide that reclamation activities, particularly those relating to control of erosion, to the extent feasible, must be conducted simultaneously with the operation and in any case must be initiated promptly after completion or abandonment of the operation on those portions of the complex that will not be subject to further disturbance. In the absence of an order by the department providing a longer period, the plan must provide that reclamation activities must be completed not more than 2 years after completion or abandonment of the operation on that portion of the complex.
(2) In the absence of emergency or suddenly threatened or existing catastrophe, an operator may not depart from an approved plan without previously obtaining from the department written approval for the proposed change.
(3) Provision must be made to avoid accumulation of stagnant water in the mined area.
(4) All final grading must be made with nonnoxious, nonflammable, noncombustible solids unless approval has been granted by the department for a supervised sanitary fill.
(5) When mining has left an open pit exceeding 2 acres of surface area and the composition of the floor or walls of the pit are likely to cause formation of acid, toxic, or otherwise pollutive solutions ("objectionable effluents") on exposure to moisture, the reclamation plan must include provisions that adequately provide for:
(a) insulation of all faces from moisture or water contact by covering to a depth of 2 feet or more with material or fill not susceptible itself to generation of objectionable effluents;
(b) processing of any objectionable effluents in the pit before they are allowed to flow or be pumped out of the pit to reduce toxic or other objectionable ratios to a level considered safe to humans and the environment by the department;
(c) drainage of any objectionable effluents to settling or treatment basins when the objectionable effluents must be reduced to levels considered safe by the department before release from the settling basin; or
(d) absorption or evaporation of objectionable effluents in the open pit itself; and
(e) prevention of entrance into the open pit by persons or livestock lawfully upon adjacent lands by fencing, warning signs, and other devices that may reasonably be required by the department.
(6) Provisions for vegetative cover must be required in the reclamation plan if appropriate to the future use of the land as specified in the reclamation plan. The reestablished vegetative cover must meet county standards for noxious weed control.
(7) The reclamation plan must provide for the reclamation of all disturbed land. Proposed reclamation must provide for the reclamation of disturbed land to comparable utility and stability as that of adjacent areas, except for open pits and rock faces that may not be feasible to reclaim in the same fashion as other disturbed lands. In the case of open pits and rock faces, the reclamation plan must provide for reclamation to a condition:
(a) of stability structurally competent to withstand geologic and climatic conditions without significant failure that would be a threat to public safety and the environment;
(b) that affords utility to humans and the surrounding natural system to the extent feasible; and
(c) that blends with the appearance of the surrounding area to the extent feasible.
(8) The reclamation plan must provide sufficient measures to ensure public safety and to prevent the pollution of air or water and the degradation of adjacent lands.
(9) A reclamation plan must be approved by the department if it adequately provides for the accomplishment of the activities specified in this section.
(10) The reclamation plan must provide for permanent landscaping and contouring to minimize the amount of precipitation that infiltrates into disturbed areas, including but not limited to tailings impoundments and waste rock dumps. The plan must also provide measures to prevent objectionable postmining ground water discharges.
(1) The reclamation plan must provide that reclamation activities, particularly those relating to control of erosion, Taking into account to the extent feasible, must be conducted simultaneously with site-specific conditions the and operation and in any case must be initiated promptly after completion or abandonment circumstances, including of the postmining use the of operation on those portions of the complex that will not mine site, disturbed lands must be subject to further disturbance. In reclaimed consistent with the absence of an order by the department providing a longer period, the plan must provide requirements and standards set forth in this section. that reclamation activities must be completed not more than 2 years after completion or abandonment of the operation on that portion of the complex.
(10) The reclamation plan must provide for permanent landscaping sufficient measures and to contouring ensure public safety and to minimize prevent the amount pollution of precipitation that infiltrates into disturbed areas, including but not limited to tailings impoundments air or water and waste rock dumps. The plan must also provide measures to prevent objectionable postmining ground water the degradation of adjacent lands. discharges.
(11) A reclamation plan must be approved by the department if it adequately provides for the accomplishment of the requirements and standards set forth in this section.
(12) The reclamation plan must provide for permanent landscaping and contouring to minimize the amount of precipitation that infiltrates into disturbed areas that are to be graded, covered, or vegetated, including but not limited to tailings impoundments and waste rock dumps. The plan must also provide measures to prevent objectionable postmining ground water discharges.
(13) The reclamation plan must include, if applicable, the requirements for postclosure monitoring of a tailings storage facility agreed to by a panel pursuant to 82-4-377.
(2) In the absence of emergency or suddenly threatened or existing catastrophe, an operator may not The reclamation depart from an approved plan without previously obtaining from the department written approval for the proposed change. must provide that reclamation activities, particularly those relating to control of erosion, to the extent feasible, must be conducted simultaneously with the operation and in any case must be initiated promptly after completion or abandonment of the operation on those portions of the complex that will not be subject to further disturbance.
(3) Provision must be made to avoid accumulation In of the stagnant water in absence of an order by the mined area. department providing a longer period, the plan must provide that reclamation activities must be completed not more than 2 years after completion or abandonment of the operation on that portion of the complex.
(4) All final grading must be made with nonnoxious, nonflammable, noncombustible solids unless approval has been In granted by the department for a supervised sanitary fill. absence of emergency or suddenly threatened or existing catastrophe, an operator may not depart from an approved plan without previously obtaining from the department written approval for the proposed change.
(5) When mining has left an open pit exceeding 2 acres Provision must be made to avoid accumulation of surface stagnant water in area the and development area to the composition of the floor extent that it serves as a host or walls of the pit are likely to cause formation of acid, toxic, breeding ground for mosquitoes or otherwise pollutive solutions ("objectionable effluents") on exposure to moisture, the reclamation plan must include provisions other disease-bearing or noxious insect life. that adequately provide for:
(a) insulation of all faces from moisture or water contact by covering to a depth of 2 feet or more with material or fill not susceptible itself to generation of objectionable effluents;
(b) processing of any objectionable effluents in the pit before they are allowed to flow or be pumped out of the pit to reduce toxic or other objectionable ratios to a level considered safe to humans and the environment by the department;
(c) drainage of any objectionable effluents to settling or treatment basins when the objectionable effluents must be reduced to levels considered safe by the department before release from the settling basin; or
(d) absorption or evaporation of objectionable effluents in the open pit itself; and
(e) prevention of entrance into the open pit by persons or livestock lawfully upon adjacent lands by fencing, warning signs, and other devices that may reasonably be required by the department.
(6) Provisions for vegetative cover All final grading must be required in the reclamation plan if appropriate to the future use of the land as made with nonnoxious, nonflammable, noncombustible solids unless approval has been granted by specified in the reclamation plan. The reestablished vegetative cover must meet county standards department for noxious weed control. a supervised sanitary fill.
(7) The reclamation plan must provide for the reclamation of all disturbed land. Proposed reclamation must When mining has left an open pit exceeding 2 acres provide for the of reclamation surface area of and disturbed land to comparable utility and stability as that the composition of adjacent areas, except for open pits and rock faces that may not be feasible to the reclaim in floor or walls of the same fashion as other disturbed lands. In the case pit are likely to cause formation of open pits and rock faces, the reclamation plan must provide for reclamation to a condition: acid, toxic, or otherwise pollutive solutions ("objectionable effluents") on exposure to moisture, the reclamation plan must include provisions that adequately
(a) insulation of stability structurally competent to withstand geologic and climatic conditions without significant failure that would be all faces from moisture or water contact by covering a threat to the public safety and the environment; faces with material or fill not susceptible itself to generation of objectionable effluents in order to mitigate the generation of objectionable
(b) that affords utility to humans and processing of any objectionable effluents in the surrounding natural system pit before they are allowed to flow or be pumped out of the extent feasible; and pit to reduce toxic or other objectionable ratios to a level considered safe to humans and the environment by the department;
(c) that blends with the appearance drainage of any objectionable effluents the to surrounding area to settling or treatment basins when the extent feasible. objectionable effluents must be reduced to levels considered safe by the department before release from the settling basin; or
(d) absorption or evaporation of objectionable effluents in the open pit itself; and
(e) prevention of entrance into the open pit by persons or livestock lawfully upon adjacent lands by fencing, warning signs, and other devices that may reasonably be required by the department.
(8) The Provisions for vegetative cover reclamation must be required in the reclamation plan must provide sufficient measures if appropriate to ensure public safety and to prevent the pollution future use of air or water and the degradation of adjacent lands. land as specified in the reclamation plan. The reestablished vegetative cover must meet county standards for
(9) A reclamation plan must be approved by the department if it adequately provides for the accomplishment of the activities specified in this section.
(9) (a) With regard to disturbed land other than open pits and rock faces, the reclamation plan must provide for the reclamation of all disturbed land to comparable utility and stability as that of adjacent areas. This standard may not be applied to require the removal of mine-related facilities that are valuable for postmining use. If the reclamation plan provides that mine-related facilities will not be removed or that the disturbed land associated with the facilities will not be reclaimed by the permittee, the following apply:
(i) The postmining use of the mine-related facilities must be approved by the department.
(ii) In the absence of a legitimate postmining use of mine-related facilities upon completion of other approved mine reclamation activities, the permittee shall comply with the reclamation requirements of this part and the reclamation plan within the time limits established in subsection (3) for mine-related facilities that had previously been identified as valuable for postmining use.
(b) With regard to open pits and rock faces, the reclamation plan must provide sufficient measures for reclamation to a condition:
(i) of stability structurally competent to withstand geologic and climatic conditions without significant failure that would be a threat to public safety and the environment;
(ii) that affords some utility to humans or the environment;
(iii) that mitigates postreclamation visual contrasts between reclamation lands and adjacent lands; and
(iv) that mitigates or prevents undesirable offsite environmental impacts.
(c) The use of backfilling as a reclamation measure is neither required nor prohibited in all cases. A department decision to require any backfill measure must be based on whether and to what extent the backfilling is appropriate under the site-specific circumstances and conditions in order to achieve the standards described in subsection (9)(b).
Reclamation plan and specific reclamation requirements
| EnactedEn. SectionSec. 9, ChapterCh. 252, Laws ofL. 1971 |
| AmendedAmd. SectionSec. 5, ChapterCh. 281, Laws ofL. 1974 |
| AmendedAmd. SectionSec. 14, ChapterCh. 39, Laws ofL. 1977 |
| Revised Codes of MontanaR.C.M. 1947, 50-1209 |
| AmendedAmd. SectionSec. 2, ChapterCh. 345, Laws ofL. 1985 |
| AmendedAmd. SectionSec. 4, ChapterCh. 453, Laws ofL. 1985 |
| AmendedAmd. SectionSec. 391, ChapterCh. 418, Laws ofL. 1995 |
| AmendedAmd. SectionSec. 1, ChapterCh. 464, Laws ofL. 1995 |