Jtl v. New Outlook, et al
Jtl v. New Outlook, et al, 2010 MT 1
Affirmed on January 5, 2010, in a 5 to 0 published opinion — 21 pages and 5,003 words .
Case
DA 09-0356
Opinion
majority
Majority
Patricia Cotter
21 pages · 5,003 words
Joined by
Mike McGrath
W. William Leaphart
Brian Morris
James C. Nelson
Smog Index: 10.4
Gunning Fog Score: 9.8
Coleman Liau Index: 11.1
Spache Readability Score: 5
Average Syllables Per Word: 1.5
Average Words Per Sentence: 10
Flesch Kincaid Grade Level: 6
Automated Readability Index: 5.1
Flesch Kincaid Reading Ease: 69.6
Dale Chall Readability Score: 6.6
Cited by
2010 MT 139N Mustang Holdings v. Zaveta DA 09-0316 2010 MT 66N Wedge v. Millard DA 09-0329 2010 MT 65 Mill Creek Limited Partnership v. Jaxon Lodge et al DA 09-0455 2010 MT 103 Conway v. Miller DA 09-0598 2010 MT 280 Matter of Estate of Burrell DA 10-0224 2011 MT 147N Coutts et al v. Cap the Rate DA 10-0598 2012 MT 54N Koemans v. Durgerians DA 11-0274 2016 MT 205 Mandell v. Bayliss DA 16-0015 2016 MT 347 Welu v. Twin Hearts DA 16-0139 2018 MT 291 Jorgensen v. Trademark Woodworks DA 18-0223Full text
OCR’d from the filed PDF
Majority
Patricia Cotter
January 5 2010
DA 09-0356
IN THE SUPREME COURT OF THE STATE OF MONTANA
2010 MT 1
JTL GROUP, Inc.,
Plaintiff and Appellee,
v.
NEW OUTLOOK, LLP,
Defendant and Appellant.
_____________________________________
NEW OUTLOOK, LLP,
Plaintiff and Appellant,
v.
JTL GROUP, Inc. and WEAVER GRAVEL, Inc.,
Defendants and Appellees.
APPEAL FROM:
District Court of the Eleventh Judicial District,
In and For the County of Flathead, Cause No. DV 2005-558B
Honorable Katherine R. Curtis, Presiding Judge
COUNSEL OF RECORD:
For Appellant:
Darrel L. Moss, Moss & Associates, P.C., Missoula, Montana
For Appellee:
Daniel D. Johns, Scott D. Hagel, Crowley Fleck, PLLP,
Kalispell, Montana
Submitted on Briefs: December 10, 2009
Decided: January 5, 2010
Filed:
__________________________________________
Clerk
2
Justice Patricia O. Cotter delivered the Opinion of the Court.
¶1
New Outlook, LLP (New Outlook), appeals from a grant of partial summary
judgment, an order of judgment following a bench trial, and an award of attorney fees in
the Eleventh Judicial District Court. We affirm.
FACTUAL AND PROCEDURAL BACKGROUND
¶2
In 2004, New Outlook was the owner and developer of a five-lot residential
subdivision near Kalispell, Montana, known as Cheery Lynn Sites. Sometime in the
summer of 2004, Ralph K. Hemp, a partner or member of New Outlook, asked Bruce
Weaver, the vice president of Weaver Gravel, Inc. (Weaver Gravel), to inspect the
subdivision and submit a bid for improvements to the subdivision. These improvements
consisted of the construction of an internal road and cul de sac, installation of water,
sewer, and other utilities, and the construction of elevated gravel building pads and
driveways.
¶3
Weaver Gravel ultimately contracted with JTL Group, Inc. (JTL), to perform the
work on the subdivision, and a bid was prepared by JTL. The bid was submitted in the
name of Weaver Gravel. The bid called for material and services to be paid for according
to the number of units of each of the components of construction improvements that were
provided to the subdivision. New Outlook accepted the bid. JTL installed road base
material, asphalt paving, water lines, sewer lines and other utilities, and concluded its
work on August 27, 2004. After completion, a dispute arose which primarily concerned
the quantity of “pit run” gravel installed as base material beneath the subdivision road.
3
¶4
On October 14, 2004, JTL filed a construction lien on the property comprising the
subdivision in the amount of $116,417.57. In May and early July 2005, JTL agreed to
execute a partial release of the construction lien as it pertained to lots 3, 4, and 5, of the
subdivision, in exchange for payment from New Outlook. The partial release allowed
New Outlook to sell these lots. These payments reduced JTL’s lien claim to $50,017.57.
¶5
In July 2005, JTL filed the instant suit against New Outlook, claiming breach of
contract, unjust enrichment, and seeking to foreclose on its construction lien. New
Outlook filed a counterclaim for slander of title against JTL. New Outlook also filed a
separate action against Weaver Gravel for breach of contract and breach of warranty.
Weaver Gravel in turn filed third-party claims against JTL, seeking indemnification. JTL
and Weaver Gravel later resolved these third-party claims. 1 Prior to trial, New Outlook
waived its breach of warranty claim against Weaver Gravel.
¶6
The statutes governing construction liens are found in Title 71, chapter 3, part 5 of
the Montana Code Annotated. Section 71-3-531(2), MCA, states that “[a] person who
may claim a construction lien pursuant to this part shall give notice of the right to claim a
lien to the contracting owner in order to claim a lien.” Sections 71-3-531(3) through (6),
MCA, describe these notice requirements with particularity. JTL did not file a notice of
its right to claim a construction lien upon New Outlook. However, § 71-3-531(1), MCA
1
JTL, through its counsel, ultimately provided a defense for Weaver Gravel against the
counterclaims asserted by New Outlook.
4
(2003),2 provides several exceptions to this notice requirement. This section reads as
follows:
The following are not required to give notice of the right to claim a lien as
required by this section:
(a) an person who furnishes services or materials directly to the
owner at the owner’s request;
(b) a wage earner or laborer who performs personal labor services
for a person furnishing any service or material pursuant to a real estate
improvement contract;
(c) a person who furnishes services or materials pursuant to a real
estate improvement contract that relates to a dwelling for five or more
families; and
(d) a person who furnishes services or materials pursuant to a real
estate improvement contract that relates to an improvement that is partly or
wholly commercial in character.
¶7
Prior to trial, New Outlook sought summary judgment on JTL’s failure to file
notice of a right to claim a construction lien. New Outlook argued that JTL’s failure to
do so rendered the construction lien unenforceable.
JTL sought partial summary
judgment that its construction lien was valid. JTL argued that the exceptions under
§ 71-3-531(1)(a) and (d), MCA, applied and that it was not required to file a notice of its
right to claim a lien in this case.
¶8
On November 5, 2007, the District Court denied New Outlook’s motion and
granted JTL’s motion for partial summary judgment, holding that JTL was exempt from
giving New Outlook notice of its right to claim a lien under § 71-3-531(1)(d), MCA. The
District Court held that the purpose of the notice requirements in § 71-3-531(1), MCA,
was to protect the individual homeowner, who is likely “not savvy” when it comes to
2
Because JTL filed its construction lien in 2004, the 2003 version of the MCA applies in this
case. In 2007, the Legislature amended portions of § 71-3-531(1), MCA. The amendments do
not affect our disposition of this appeal.
5
construction contracts and the payments of accounts and liens.
The District Court
determined these policy concerns were not present since New Outlook is a real estate
developer. In addition, the District Court concluded that it would look to the nature of
the enterprise to determine whether it is “commercial” in character. In this case, the
improvement for which JTL filed its lien was not a house or dwelling, but was instead a
road, which could not be characterized as residential. Accordingly, notice of the right to
claim the lien was not required and JTL’s attempts to foreclose on its construction lien
could go forward.
¶9
A bench trial on the parties’ claims was scheduled to commence on December 3,
2007. On November 29, New Outlook filed a motion to disqualify the presiding judge,
the Hon. Katherine R. Curtis, for cause. The trial was postponed by an order of this
Court while a substitute judge was brought in and the motion was resolved. The motion
was ultimately decided against New Outlook on February 5, 2008, and attorney fees and
costs were awarded to JTL following a hearing.
¶10
The bench trial was held on June 23-25, 2008. The District Court issued findings
of fact, conclusions of law, and an order for partial judgment on August 1, 2008. In its
findings, the District Court determined that New Outlook conceded that it owed
$21,665.57 to Weaver Gravel, but disputed the $50,017.57 claimed by JTL. The District
Court determined that the money claimed was actually owed to JTL and not Weaver
Gravel, because it was JTL that actually performed the work and filed a construction lien
on the subject property.
6
¶11
The District Court noted that JTL and New Outlook presented conflicting
testimony at trial regarding the amount of pit run gravel supplied by JTL. Ultimately, the
District Court determined that JTL failed to meet its burden of proof with regard to the
additional amount claimed in its lien over and above the amount New Outlook conceded
that it owed. The District Court further found that JTL did not file its lien in bad faith or
with actual malice, and did not deliberately inflate the amount it claimed it was owed on
the lien.
¶12
In its conclusions of law, the District Court determined that JTL’s lien was valid
under LHC, Inc. v. Alvarez, 2007 MT 123, 337 Mont. 294, 160 P.3d 502. The District
Court further concluded that JTL had complied with all the procedural requirements of
Montana’s construction lien statutes, and that it was owed $21,665.57, the amount which
New Outlook conceded it owed for the work done on the subdivision. The District Court
also awarded JTL prejudgment interest.
Further, the District Court dismissed New
Outlook’s slander of title claim against JTL since it concluded that JTL’s lien was valid.3
¶13
The District Court also denied New Outlook’s claim for breach of contract against
Weaver Gravel. The District Court concluded that this claim was based on a prayer for
indemnification for any amounts that New Outlook might be ordered to pay over and
above the contract amount owed to Weaver Gravel. Since the District Court found that
no extra amount was owed by New Outlook, it denied New Outlook’s breach of contract
claim against Weaver Gravel.
3
The District Court also denied New Outlook’s claims for punitive damages against JTL. This
ruling has not been appealed.
7
¶14
The District Court also awarded JTL and Weaver Gravel costs and reasonable
attorney fees. JTL and Weaver Gravel were both represented by the same attorneys.
Pursuant to the District Court’s order, JTL and Weaver Gravel submitted a bill of costs
and an affidavit in support of an award of attorney fees. New Outlook filed objections.
The parties were given an opportunity to request a hearing on attorney fees on or before
JTL/Weaver Gravel’s response to New Outlook’s objections were due, or the hearing was
deemed waived. New Outlook did not timely request a hearing.
¶15
On April 29, 2009, the District Court entered findings of fact, conclusions of law,
and its order on attorney fees and costs. JTL’s affidavits sought a total of $119,072.50 in
attorney fees. The District Court determined in its findings that the affidavits itemized
the hourly rates of the attorneys, contained descriptions of the work performed and hours
expended in performing the work, thus representing the “lodestar fee” pursuant to
Laudert v. Richland Co. Sheriff’s Dept., 2001 MT 287, 307 Mont. 403, 38 P.3d 790.
¶16
New Outlook raised several objections to JTL’s claimed amount of attorney fees.
New Outlook argued that much of the work of JTL’s counsel was excessive, redundant,
or otherwise unnecessary, and that the time entries were either duplicative or not
sufficiently detailed. New Outlook also argued that JTL improperly sought attorney fees
for taking and defending depositions which were not used at trial, as well as
non-recoverable fees for expert witnesses. Further, New Outlook contended that JTL was
not entitled to attorney fees incurred in responding to New Outlook’s motions, and may
not recover “fees for fees”; i.e., attorney fees incurred in proving the right to recover
reasonable attorney fees.
8
¶17
The District Court rejected most of New Outlook’s arguments regarding the
reasonableness of JTL’s claimed attorney fees. The District Court determined that the
billing statements were sufficiently detailed and not for the most part excessive or
redundant. The District Court also determined that New Outlook had failed to present
evidence or expert witness testimony in support of its arguments against the award, and
had failed to overcome the strong presumption that JTL’s lodestar calculation was
reasonable. However, the District Court did conclude that some amounts billed were
unwarranted and eliminated approximately $7,600 in claimed fees.
¶18
The District Court then evaluated the reasonableness of JTL’s attorney fees under
the following seven-factor test described in Plath v. Schonrock, 2003 MT 21, 314 Mont.
101, 64 P.3d 684:
The reasonableness of attorney fees must be ascertained under the facts of
each case. This Court has stated that in determining what constitutes
reasonable attorney fees, the following factors should be considered as
guidelines: (1) the amount and character of the services rendered; (2) the
labor, time and trouble involved; (3) the character and importance of the
litigation in which the services were rendered; (4) the amount of money or
the value of the property to be affected; (5) the professional skill and
experience called for; (6) the attorneys’ character and standing in their
profession; and (7) the results secured by the services of the attorneys.
Plath, ¶ 36 (citing Morning Star Enterprises, Inc. v. R.H. Grover, Inc., 247 Mont. 105,
114, 805 P.2d 553, 558 (1991)).
¶19
The District Court carefully analyzed the factors supporting each element of the
test, and concluded the claimed fees were reasonable under Plath. For purposes of this
Opinion, we deem it unnecessary to recount the entire analysis. The District Court also
9
noted that § 71-3-124(1), MCA (2003)4, provides for a mandatory award of attorney fees
to the prevailing party in a construction lien case. This statute reads as follows:
In an action to foreclose any of the liens provided for by part 3, 4, 5, 6, 8 or
10 of this chapter, the court shall allow as costs the money paid and
attorney fees incurred for filing and recording the lien and reasonable
attorney fees in the district and supreme courts. The costs and attorney
fees must be allowed to each claimant whose lien is established, and the
reasonable attorney fees must be allowed to the defendant against whose
property a lien is claimed if the lien is not established.
(Emphasis added.)
¶20
In its conclusions of law, the District Court concluded that JTL was entitled to its
recoverable costs under Title 25, chapter 10, part 2, and that New Outlook had waived its
objections to costs because its objections were untimely. Similarly, the District Court
concluded that New Outlook waived its right to a hearing on attorney fees by not filing a
request for a hearing until approximately 3 months after the final deadline to request a
hearing had passed.
¶21
Under § 71-3-124(1), MCA, attorney fees are available to a party establishing a
construction lien for “reasonable attorney fees in the district and supreme courts.” The
District Court concluded that attorney fees incurred in the taking and defending of
depositions were covered by this statute, even if not used at trial. Similarly, the District
Court determined that fees incurred in responding to New Outlook’s various motions
were also covered under § 71-3-124(1), MCA.
4
The 2007 Legislature also made changes to this statute which are not relevant to the instant
appeal.
10
¶22
Finally, the District Court concluded that it was not possible to segregate the
attorney fees incurred among the construction lien foreclosure action, and the other
claims asserted in this case. Because JTL, as the prevailing party, was entitled to attorney
fees under Blue Ridge Homes, Inc. v. Thein, 2008 MT 264, 345 Mont. 125, 191 P.3d 374,
the District Court awarded JTL most of the fees claimed. In this connection, the District
Court concluded that New Outlook had failed to produce any evidence or expert
testimony sufficient to overcome the “strong presumption” that the lodestar amount
claimed by JTL was reasonable. See Laudert, ¶ 17. Based on these conclusions, the
District Court determined that JTL was entitled to an award of $111,413.50 in attorney
fees and $791.50 in costs.
¶23
After judgment was entered, New Outlook moved to amend or alter the judgment.
New Outlook contended that JTL had failed to offer sufficient evidence to establish the
construction lien, and that much of the evidence upon which JTL relied was inadmissible
hearsay. The District Court denied the motion, noting that New Outlook did not object to
the evidence which it was now contesting. The District Court noted that most of the
objections put forth by New Outlook in its motion to alter or amend were being raised
post-trial for the first time.
¶24
New Outlook now appeals from these decisions of the District Court, presenting
the following issues on appeal:
¶25
Issue One: Did the District Court err in concluding that JTL was not required to
give New Outlook notice of its right to claim the construction lien prior to its filing?
11
¶26
Issue Two: Did the District Court err in concluding that JTL had established the
construction lien in this case?
¶27
Issue Three: Did the District Court err in denying New Outlook’s claim for
breach of contract against Weaver Gravel?
¶28
Issue Four: Did the District Court abuse its discretion in awarding JTL attorney
fees and costs?
STANDARD OF REVIEW
¶29
We review a district court’s ruling on summary judgment de novo. We review a
district court’s conclusions of law to determine whether they are correct and its findings
of fact to determine whether they are clearly erroneous. Revelation Indus., Inc. v. St.
Paul Fire & Marine Ins. Co., 2009 MT 123, ¶ 13, 350 Mont. 184, 206 P.3d 919.
¶30
We review findings of fact in a civil bench trial to determine if they are supported
by substantial credible evidence. DeNiro v. Gasvoda, 1999 MT 129, ¶ 9, 294 Mont. 478,
982 P.2d 1002. This Court “must view the evidence in the light most favorable to the
prevailing party.” DeNiro, ¶ 9. Conclusions of law in this context are also reviewed for
correctness. DeNiro, ¶ 9.
¶31
We review for abuse of discretion a district court’s denial of a motion to alter or
amend a judgment pursuant to M. R. Civ. P. 59(g). We also review for an abuse of
discretion a district court’s order granting or denying attorney fees. Blue Ridge Homes,
¶ 20.
¶32
Issue One: Did the District Court err in concluding that JTL was not required to
give New Outlook notice of its right to claim the construction lien prior to its
filing?
12
¶33
In its grant of partial summary judgment, the District Court determined that JTL
was not required to give notice to New Outlook of its right to claim a construction lien by
virtue of § 71-3-531(1)(d), MCA. See Opinion, ¶¶ 6-8. New Outlook claims this was
error. It argues the District Court erred when it determined that JTL was exempted from
the notice requirements in § 71-3-531(2), MCA. New Outlook argues that, under the
construction lien statutes, the District Court was required to look to the nature and
character of the improvement to determine if it was “commercial in character.” Instead
of looking to the use of the improvement, the District Court considered the subjective
intent of the developer in having the improvements constructed to ascertain whether the
improvement was “commercial” or “residential” in character. Here, New Outlook argues
it is undisputed that the services and materials provided by JTL were for improvements in
a residential subdivision with no commercial use.
Thus, the improvements was
residential, not commercial, in character. By relying upon the fact that New Outlook
intended to sell the subdivision for a profit in order to conclude that the improvements
were commercial, New Outlook argues the District Court wrongly considered the
subjective intent of the developer and in effect altered the plain meaning of the statute.
¶34
JTL urges us to affirm. JTL contends that the infrastructure improvements it
provided constituted improvements with an undeniable commercial purpose—i.e., the
creation of a sales inventory of buildings lots. In this connection, JTL argues these
specific improvements are not conceptually and substantively distinguishable from the
construction of a grocery store or office complex for later resale. JTL argues that the
character of a real estate development for purposes of the construction lien statutes
13
cannot be dissociated from the commercial nature of the venture within which it was
created.
¶35
JTL also draws the Court’s attention to the circumstances surrounding the creation
of the construction lien which attached to the New Outlook subdivision. JTL notes that
under § 71-3-535(5), MCA, a construction lien attaches at the commencement of the
work. When JTL provided services and materials, the subdivision was devoid of any
residential improvements and no portion was owned by individual landowners. Further,
the property was held by a partnership that was developing the subdivision for a profit.
Following the completion of JTL’s work, the property at issue contained nothing more
than “empty building lots with newly installed roadways, water, sewer, and other utilities,
placed in the stream of commerce for immediate resale.” JTL contends that nothing in
the gravel, asphalt, or water and sewer lines is distinctly “residential,” or
non-commercial, in character, and that the District Court did not err in concluding that
the exception in § 71-3-531(1)(d), MCA, applies.
¶36
We agree with JTL and affirm the District Court. We interpret statutes according
to their plain language; if the language of the statute is clear on its face, this Court looks
no further. Haney v. Mahoney, 2001 MT 201, ¶ 7, 306 Mont. 288, 32 P.3d 1254. Section
71-3-531(1)(d), MCA, exempts a party seeking a construction lien from the notice
requirements in § 71-3-531(2), MCA, if the “services or materials pursuant to a real
estate improvement contract . . . [relate] to an improvement that is partly or wholly
commercial in character.”
Here, JTL provided “pit run” gravel for an internal
subdivision road. As JTL correctly notes, its construction lien attached at a time when
14
there were no residential improvements and no property owned by individual
homeowners. Further, as noted by the District Court, the improvement for which JTL
filed its lien was not a house or dwelling, but was instead a road, which could not be
characterized as “residential” in nature.
¶37
For the foregoing reasons, the improvements provided by JTL were “partly or
wholly commercial in character,” and therefore the exception to the notice requirement in
§ 71-3-531(1)(d), MCA, clearly applies. Thus, we affirm the District Court regarding
this issue.
¶38
Issue Two: Did the District Court err in concluding that JTL had established the
construction lien in this case?
¶39
New Outlook argues that the District Court erred when it concluded that JTL had
established a valid construction lien. JTL argues that the construction lien statement filed
by JTL and admitted into evidence does not establish when JTL furnished materials and
services, and is based on nothing more than inadmissible hearsay and self-serving
statements made by JTL’s witnesses at trial. New Outlook also argues that JTL failed to
establish at trial that it provided service on New Outlook of its construction lien. New
Outlook further argues that the property described in the construction lien does not
contain a description of the property sufficient to identify it as required under
§ 71-3-535(3)(b), MCA.
¶40
JTL offers a persuasive counterargument to which New Outlook offers no reply.5
First, JTL notes the District Court’s finding that New Outlook essentially conceded that it
5
New Outlook did not file a reply brief on appeal.
15
owed JTL $21,665.57 for materials it provided. Second, it notes that the issues now
raised by New Outlook were never raised in the pretrial order, or preserved for appeal.
Instead, New Outlook raised them for the first time in its post-trial Rule 59(g) motions.
JTL further observes that the construction lien, which New Outlook now claims is
inadmissible hearsay, was admitted into evidence without objection. For these reasons,
JTL argues that New Outlook’s arguments should be rejected under Alvarez.
Alternatively, JTL contends that it did in fact present sufficient evidence to support the
construction lien.
¶41
In its denial of New Outlook’s Rule 59(g) motions, the District Court noted that
New Outlook had failed to raise these same issues prior to trial, and therefore waived
them. We agree. The arguments now presented by New Outlook were raised for the first
time in post-trial motions, and are therefore waived. Alvarez, ¶¶ 20-21. Similarly, New
Outlook has waived its ability to challenge the admissibility of JTL’s construction lien
statement, since it failed to object to its admissibility at trial. See City of Helena v.
Kortum, 2003 MT 290, ¶ 16, 318 Mont. 77, 78 P.3d 882. Therefore, we affirm the
District Court on this issue.
¶42
Issue Three: Did the District Court err in denying New Outlook’s claim for
breach of contract against Weaver Gravel?
¶43
New Outlook’s claim for breach of contract against Weaver Gravel was based on
the prospect that it might have to pay JTL an amount in excess of the $21,665.57 that
New Outlook conceded it owed. Having determined that New Outlook did not owe
anything over and above this amount, the District Court denied the breach of contract
16
claim. New Outlook claims this was error, complaining that it now owes attorney fees
and prejudgment interest in excess of $157,000 as a result of Weaver Gravel’s breach of
contract. New Outlook argues that the District Court’s decision should be reversed so
that the breach of contract claims can now go forward.
¶44
JTL urges us to affirm. JTL notes that New Outlook made it “abundantly clear” in
the pretrial order that the basis of its breach of contract claim was the prospect that it
might have to pay JTL some amount in excess of what it conceded it owed to Weaver
Gravel. Since the District Court found that it did not owe an amount in excess of this
figure, it properly dismissed the breach of contract claim.
JTL contends that the
additional amounts now owed by New Outlook for attorney fees and prejudgment interest
are not relevant to the breach of contract claim it posited at trial.
¶45
We agree with JTL and affirm the District Court. The additional amounts now
owed by New Outlook are based on attorney fees and prejudgment interest and are not
relevant to the breach of contract claims it presented at trial. The District Court did not
err in rejecting those claims once it determined that New Outlook did not owe Weaver
Gravel an amount in excess of $21,665.57.
¶46
Issue Four: Did the District Court abuse its discretion in awarding JTL attorney
fees and costs?
¶47
Finally, New Outlook contends that the District Court erred in awarding attorney
fees to JTL. First, New Outlook argues that JTL failed to present any evidence or
third-party expert testimony to support an award of attorney fees. Instead, New Outlook
contends that JTL relied upon the “self-serving” affidavits of its attorneys to establish an
17
award of attorney fees. Second, New Outlook asserts that many of the fees incurred by
JTL in this case were unrelated to the construction lien, and should not have been
awarded by the District Court. Third, New Outlook argues that attorney fees incurred in
connection with the taking and defending of depositions, as well as those fees related to
the presentation of expert testimony, are not recoverable in this case. Fourth, New
Outlook generally contends that JTL’s claim of over 190 hours of trial preparation
attorney fees in October and November 2007 is excessive. Fifth, New Outlook claims
that the District Court erred in awarding JTL attorney fees it incurred in establishing its
right to attorney fees—i.e., “fees for fees.” For these reasons, New Outlook argues the
District Court’s award of attorney fees should be reversed.
¶48
JTL contends that the District Court did not abuse its discretion in awarding
attorney fees, and that its decision should be upheld. JTL notes that New Outlook filed
untimely objections to the costs, did not request a hearing on attorney fees, and did not
present any expert testimony or evidence to overcome the presumption that the lodestar
calculation was correct.
¶49
JTL also argues there was no injustice in the District Court’s decision. JTL
maintains that New Outlook unnecessarily prolonged this case, engaged in discovery
abuse, filed numerous motions, and set forth numerous contentions in the pretrial order
which JTL had to spend time analyzing and preparing for, even though New Outlook did
not litigate many of those contentions at trial. Further, JTL claims that New Outlook
indentified several hundred pages of documents, and approximately 112 exhibits, which
it had to analyze and consider in order to be properly prepared for trial.
18
¶50
JTL also contends that the District Court correctly determined that all of the
claims in this case were inextricably intertwined, involving the same facts and same
witnesses, and that it was not possible to segregate the time among claims. Under Blue
Ridge Homes, JTL argues the award of attorney fees was appropriate.
¶51
We review an award of attorney fees for an abuse of discretion. Blue Ridge
Homes, ¶ 20. An abuse of discretion occurs when the district court acts arbitrarily
without the employment of conscientious judgment or exceeds the bounds of reason
resulting in substantial injustice. James Talcott Const., Inc. v. P & D Land Enterprises,
2006 MT 188, ¶ 62, 333 Mont. 107, 141 P.3d 1200.
¶52
We agree with JTL that the District Court did not abuse its discretion when it
awarded attorney fees. The construction lien statutes contain fee-shifting provisions for
the party which prevails in establishing a lien. As we stated in Laudert, “there is a strong
presumption, given the rationale behind fee-shifting provisions, that the lodestar fee is a
reasonable fee.” Laudert, ¶ 17 (citing Pennsylvania v. Delaware Valley Citizens’ Council
for Clean Air, 478 U.S. 546, 565, 106 S. Ct. 3088, 3098 (1986)). Here, the lodestar fee
established by JTL was entitled to this presumption of reasonableness, and New Outlook
failed to produce sufficient evidence to overcome this presumption. As noted by JTL,
New Outlook waived its right to a hearing on attorney fees, and presented no expert
testimony or evidence to demonstrate that JTL’s lodestar calculation was unreasonable.
¶53
Furthermore, the District Court correctly determined that the claims in this case
were intertwined, and acted within its discretion when it awarded JTL attorney fees based
on the construction lien statutes. See Blue Ridge Homes, ¶ 78 (noting that a district court
19
may consider intertwined claims, involving the same factual and legal issues, for
purposes of calculating attorney fees and costs). Similarly, the award of attorney fees
incurred in the taking and defending of depositions was reasonable under § 71-3-124(1),
MCA, as this statute allows the party who establishes a construction lien to recover fees
incurred “in the district and supreme courts.” Finally, we specifically held in Blue Ridge
Homes, that “fees for fees” are recoverable in actions which establish a construction lien.
Blue Ridge Homes, ¶ 81. In sum, New Outlook has failed to demonstrate how, under the
circumstances of this case, the District Court’s award of attorney fees was arbitrary,
unreasonable, or resulted in substantial injustice to New Outlook.
CONCLUSION
¶54
The District Court did not err in concluding that JTL was exempt from giving New
Outlook notice of its right to file a construction lien in this case, nor did it err in
determining that JTL successfully established a construction lien. Further, the District
Court did not err in denying New Outlook’s breach of contract claims against Weaver
Gravel. Finally, we conclude the District Court did not abuse its discretion in awarding
attorney fees. Affirmed.
/S/ PATRICIA O. COTTER
We concur:
/S/ MIKE McGRATH
/S/ W. WILLIAM LEAPHART
/S/ BRIAN MORRIS
/S/ JAMES C. NELSON
20