Mont. Code Ann. § 76-3-604 (1)

(2015)

Review of subdivision application – review for required elements and sufficiency of information

(1) (a) A subdivision application is considered to be received on the date of delivery to the reviewing agent or agency and when accompanied by the review fee submitted as provided in 76-3-602.

(b) Within 5 working days of receipt of a subdivision application, the reviewing agent or agency shall determine whether the application contains all of the listed materials as required by 76-3-504(1)(a) and shall notify the subdivider or, with the subdivider's written permission, the subdivider's agent of the reviewing agent's or agency's determination. If the reviewing agent or agency determines that elements are missing from the application, the reviewing agent or agency shall identify those elements in the notification.

(2) (a) Within 15 working days after the reviewing agent or agency notifies the subdivider or the subdivider's agent that the application contains all of the required elements as provided in subsection (1), the reviewing agent or agency shall determine whether the application and required elements contain detailed, supporting information that is sufficient to allow for the review of the proposed subdivision under the provisions of this chapter and the local regulations adopted pursuant to this chapter and shall notify the subdivider or, with the subdivider's written permission, the subdivider's agent of the reviewing agent's or agency's determination.

(b) If the reviewing agent or agency determines that information in the application is not sufficient to allow for review of the proposed subdivision, the reviewing agent or agency shall identify the insufficient information in its notification.

(c) A determination that an application contains sufficient information for review as provided in this subsection (2) does not ensure that the proposed subdivision will be approved or conditionally approved by the governing body and does not limit the ability of the reviewing agent or agency or the governing body to request additional information during the review process.

(3) The time limits provided in subsections (1) and (2) apply to each submittal of the application until:

(a) a determination is made that the application contains the required elements and sufficient information; and

(b) the subdivider or the subdivider's agent is notified.

(4) After the reviewing agent or agency has notified the subdivider or the subdivider's agent that an application contains sufficient information as provided in subsection (2), the governing body shall approve, conditionally approve, or deny the proposed subdivision within 60 working days or 80 working days if the proposed subdivision contains 50 or more lots, based on its determination of whether the application conforms to the provisions of this chapter and to the local regulations adopted pursuant to this chapter, unless:

(a) the subdivider and the reviewing agent or agency agree to an extension or suspension of the review period, not to exceed 1 year; or

(b) a subsequent public hearing is scheduled and held as provided in 76-3-615.

(5) (a) If the governing body fails to comply with the time limits under subsection (4), the governing body shall pay to the subdivider a financial penalty of $50 per lot per month or a pro rata portion of a month, not to exceed the total amount of the subdivision review fee collected by the governing body for the subdivision application, until the governing body denies, approves, or conditionally approves the subdivision.

(b) The provisions of subsection (5)(a) do not apply if the review period is extended or suspended pursuant to subsection (4).

(6) If the governing body denies or conditionally approves the proposed subdivision, it shall send the subdivider a letter, with the appropriate signature, that complies with the provisions of 76-3-620.

(7) (a) The governing body shall collect public comment submitted at a hearing or hearings regarding the information presented pursuant to 76-3-622 and shall make any comments submitted or a summary of the comments submitted available to the subdivider within 30 days after conditional approval or approval of the subdivision application and preliminary plat.

(b) The subdivider shall, as part of the subdivider's application for sanitation approval, forward the comments or the summary provided by the governing body to the:

(i) reviewing authority provided for in Title 76, chapter 4, for subdivisions that will create one or more parcels containing less than 20 acres; and

(ii) local health department or board of health for proposed subdivisions that will create one or more parcels containing 20 acres or more and less than 160 acres.

(8) (a) For a proposed subdivision that will create one or more parcels containing less than 20 acres, the governing body may require approval by the department of environmental quality as a condition of approval of the final plat.

(b) For a proposed subdivision that will create one or more parcels containing 20 acres or more, the governing body may condition approval of the final plat upon the subdivider demonstrating, pursuant to 76-3-622, that there is an adequate water source and at least one area for a septic system and a replacement drainfield for each lot.

(9) (a) Review and approval, conditional approval, or denial of a proposed subdivision under this chapter may occur only under those regulations in effect at the time a subdivision application is determined to contain sufficient information for review as provided in subsection (2).

(b) If regulations change during the review periods provided in subsections (1) and (2), the determination of whether the application contains the required elements and sufficient information must be based on the new regulations.

Opinions construing this section

4 opinions
2014 MT 207 Aug 5, 2014 Affirmed in part, reversed in part
Lewis & Clark Co. v. Hampton
Dissenting by Laurie McKinnon · 4 to 1
601, -622, MCA. ¶59 After submission of a complete subdivision application, the governing body may approve, conditionally approve, or deny the application. Section 76-3-604, MCA. Conditional approval is valid for at least one year, during which time the governing body may not impose additional conditions. Section 76-3-610, MCA. The de
2009 MT 182 May 22, 2009 Reversed
Citizens v. Sanders Co. Commissioners
Majority by Jim Rice · 5 to 0
r months after the EA was prepared and deem such information part of the EA” and therefore the Board “had a duty to reject the EA as being incomplete under § 76-3-604(2)(b), MCA as well as its own regulations.” Additionally, CRD argues that, even if all the information submitted by the Developer was to be considered, the application
2008 MT 249 Jul 15, 2008 Affirmed
Bitterrooters for Planning v. Board of County Commissioners
Majority by Patricia Cotter · 5 to 0
s complete and contained adequate supporting information, the County was required to approve, conditionally approve, or deny the application within sixty days. Section 76-3-604, MCA (2005). The County failed to meet these deadlines. Meanwhile, in November 2006, before these applications 2 were reviewed, Ravalli County voters enacted an
2007 MT 118 May 22, 2007 Affirmed in part, reversed in part
Fielder v. Sanders County Bocc
Majority by Brian Morris · 5 to 0
erning body may 10 conditionally approve a preliminary plat and enumerate conditions that the developer needs to meet to ensure approval of the final plat. Section 76-3-604, MCA (2003). The Attorney General noted that the local government may not impose any additional conditions as a prerequisite to a final plat approval after it has a
Official Annotations archive.org, 2015 edition
History:
En. Sec. 8, Ch. 500, L. 1973
Amd. Sec. 6, Ch. 334, L. 1974
Amd. Sec. 3, Ch. 498, L. 1975
Amd. Sec. 1, Ch. 555, L. 1977
R.C.M. 1947, 11-3866(part)
Amd. Sec. 1, Ch. 236, L. 1999 (HB 300 - Ohs, Karl (R) HD 33)
Amd. Sec. 24, Ch. 582, L. 1999 (SB 97 - Stang, Spook (D) SD 36)
Amd. Sec. 4, Ch. 527, L. 2001 (HB 543 - Brown, Roy (R) HD 14)
Amd. Sec. 7, Ch. 298, L. 2005 (SB 116 - Laible, Rick (R) SD 44)
Amd. Sec. 5, Ch. 302, L. 2005 (SB 290 - Mangan, Jeff (D) SD 12)
Amd. Sec. 2, Ch. 405, L. 2009 (SB 305 - Tutvedt, Bruce (R) SD 3)
Amd. Sec. 3, Ch. 109, L. 2013 (SB 40 - Buttrey, Edward (R) SD 13)