4 82-4-301 1 82-4-302 3 82-4-303 82-4-304 82-4-305 82-4-306 82-4-307 82-4-308 82-4-309 82-4-310 82-4-311 82-4-312 1 82-4-313 82-4-314 82-4-315 82-4-321 82-4-322 82-4-323 82-4-331 82-4-332 82-4-334 2 82-4-335 3 82-4-336 1 82-4-337 82-4-338 82-4-339 82-4-340 82-4-341 82-4-342 82-4-349 82-4-350 3 82-4-351 82-4-352 82-4-353 82-4-354 1 82-4-355 82-4-356 82-4-357 1 82-4-360 1 82-4-361 82-4-362 82-4-371 82-4-372 82-4-390

Mont. Code Ann. § 82-4-341 (9)

(2001)

Compliance -- reclamation by department

(1) The department shall cause the permit area to be inspected at least annually to determine whether the permittee has complied with this part, the rules adopted under this part, or the permit.

(2) The permittee shall proceed with reclamation as scheduled in the approved reclamation plan or as required pursuant to subsection (8). Following written notice by the department noting deficiencies, the permittee shall commence action within 30 days to rectify these deficiencies and shall diligently proceed until the deficiencies are corrected. Deficiencies that also violate other laws that require earlier rectification must be corrected in accordance with the applicable time provisions of those laws. The department may extend performance periods referred to in 82-4-336 and in this section for delays clearly beyond the permittee's control, but only when the permittee is, in the opinion of the department, making every reasonable effort to comply.

(3) Within 30 days after notification by the permittee and when, in the judgment of the department, reclamation of a unit of disturbed land area is properly completed, the department shall provide the public notice and conduct any hearing requested pursuant to 82-4-338. As soon as practicable after notice and hearing, the permittee must be notified in writing and the bond on the area must be released or decreased proportionately to the acreage included within the bond coverage.

(4) The department shall cause the bond to be forfeited if:

(a) reclamation of disturbed land is not pursued in accordance with the reclamation plan and the permittee has not commenced action to rectify deficiencies within 30 days after notification by the department;

(b) reclamation is not properly completed in conformance with the reclamation plan within 2 years after completion or abandonment of operation on any fraction of the permit area or within a longer period that may have been authorized under this part; or

(c) after default by the permittee, the surety either refuses or fails to perform the work to the satisfaction of the department within the time required.

(5) The department shall notify the permittee and the surety by certified mail. If the bond is not paid within 30 days after receipt of the notice, the attorney general, upon request of the department, shall bring an action on behalf of the state in district court.

(6) The department may, with the staff, equipment, and material under its control or by contract with others, take any necessary actions for required reclamation of the disturbed lands according to the existing reclamation plan or a modified reclamation plan if the department makes a written finding that the modifications are necessary to prevent a violation of Title 75, chapter 2 or 5, or to prevent a substantial reclamation failure. Except in an environmental emergency, work provided for in this section must be let on the basis of competitive bidding. The department shall keep a record of all necessary expenses incurred in carrying out the work or activity authorized under this section, including a reasonable charge for the services performed by the state's personnel and the state's equipment and materials used. The surety is liable to the state to the extent of the bond. The permittee is liable for the remainder of the cost. Upon completion of the reclamation, the department shall return to the surety any amount not expended, including any unexpended interest accrued on bond proceeds, unless otherwise agreed to in writing by the surety.

(7) In addition to the other liabilities imposed by this part, failure to commence an action to remedy specific deficiencies in reclamation within 30 days after notification by the department or failure to satisfactorily complete reclamation work on any segment of the permit area within 2 years or within a longer period that the department may permit on the permittee's application or on the department's own motion, after completion or abandonment of operations on any segment of the permit area, constitutes sufficient grounds for cancellation of a permit or license and refusal to issue another permit or license to the applicant. A cancellation action may not be effected while an appeal is pending from any ruling requiring the cancellation of a permit or license.

(8) (a) If at the time of bond review pursuant to 82-4-338 no mineral extraction or ore processing has occurred on a mine permit area for the past 5 years, the department shall determine whether further suspension of the operation will create conditions that will cause violations of Title 75, chapter 2 or 5, or significantly impair reclamation of disturbed areas. If the department determines in writing that violations of Title 75, chapter 2 or 5, or significant impairment of reclamation will occur, the department shall notify the permittee that the permittee shall, within a reasonable time specified in the notice, abate the conditions or commence reclamation. The department may grant reasonable extensions of time for good cause shown. If the permittee does not abate the conditions or commence reclamation within the time specified in the notice and any extensions, the department shall order either that the condition be abated or that reclamation be commenced.

(b) The permittee may request a hearing on the order by submitting a written request for hearing within 30 days of receipt of the order. A request for hearing stays the order pending a final decision, unless the department determines in writing that the stay will create an imminent threat of significant environmental harm or will significantly impair reclamation.

Official Annotations archive.org, 2001 edition
History:
En. Sec. 13, Ch. 252, L. 1971
Amd. Sec. 8, Ch. 281, L. 1974
R.C.M. 1947, 50-1213
Amd. Sec. 3, Ch. 204, L. 1995
Amd. Sec. 396, Ch. 418, L. 1995
Amd. Sec. 6, Ch. 507, L. 1999 (HB 183 - Dale, Rick (R) HD 39)
Amd. Sec. 8, Ch. 488, L. 2001 (HB 69 - McCann, Matt (D) HD 92)